A falling delay rate can make delivery pressure appear to be easing. Put delayed quantities beside it, however, and the workload may tell a different story: a smaller proportion of a much larger requirement can still mean more delayed units.
In a review, I would separate relative performance from the amount of work to resolve. A change in one does not settle the other.
Align numerator and denominator
Before dividing delayed units by units due, define how the due population is grouped. Is it based on the customer’s original required period or the order-placement period? Are we measuring units, order lines or whole orders? These definitions answer different questions.
Fix the product scope, exclusions and cut-off before comparing periods. Keep the original requested milestone separate from the latest schedule, so rescheduling does not erase the earlier variance.
An entirely fictional training example
Suppose practice period A has 100 units due and 40 delayed: a 40% delay rate. Practice period B has 200 due and 60 delayed: a 30% delay rate. These invented figures illustrate the relationship and do not represent a real project.
B has a lower delay rate and a larger delayed quantity. The relative proportion has fallen, but that alone does not show that remaining work has decreased. We still need to know which late deliveries are complete and which remain open.
Delayed does not always mean still unshipped
Within the same population, distinguish deliveries completed late within the period, completed in a later period and still incomplete at the cut-off. If only an estimated schedule is available, retain that label rather than reporting actual dispatch.
A useful weekly question is:
How have the due population and delayed quantity changed? Which delayed records have completion evidence, and which remain open? Who owns the remainder, and which milestone will be checked next?
This turns a percentage into a list someone can act on. For training, ask a colleague to explain what information is missing from a downward trend line before they can plan next week’s recovery work. Correct arithmetic is only the beginning of a useful review.
Related: A shorter average lead time: what about the orders still open?.
Drawn from questions raised in a periodic work review. Identities, business figures and project details have been removed. Checklists and sample wording are for similar situations; they do not establish a completed outcome.